Capital Development Board - 120-255-028, Phase 2 - Repair Interior Finish Damage

Agency: Capital Development Board

Location: Vienna, Johnson County, Illinois

BASE BID:

This project involves interior repairs and replacement of ceiling and floor finishes due to roof leaks at the Shawnee Correctional Center, east of Vienna, Illinois.

Building C1137 Administration Building: Replace ceiling finishes and substrate flooring, light fixtures and painting in designated spaces.

Building C1138 Dietary Building: Replace ceiling finishes and substrate, and light fixtures of designated spaces.


Copies of the documents are available and may be obtained from our office by depositing a check in the amount of $125.00 for each set of documents so obtained, made payable to the Eggemeyer Associates Architects, Inc.

This project has a construction estimate of: under $300,000.00


Shawnee Correctional Center, 6665 State Rt. 146 E., Vienna, IL 62995